At the first power unit of Belarusian NPP the “Power start-up” stage continues. This stage provides for the power unit operation modes at various power levels (up to 500 MW), as well as checking the stability of the power system operation when it is repeatedly reduced.
In the course of the tests carried out, in accordance with the program of this stage, it was revealed the need to replace individual electrical measuring equipment. Work on the replacement of this equipment is carried out in accordance with the technological regulations. At present, the power unit is undergoing tests and work in accordance with the milestone program. All technological systems are operating in regular mode.