Wednesday, 31 May 2023

The stage of pilot operation of the second power unit began at BelNPP

Written by Department of information and public relations

The corresponding permission was issued by Gosatomnadzor the day before.

The stage of pilot operation provides for a phased increase in the power of the reactor system of the power unit from 50% to 100% with a large number of tests of technological systems and equipment in different operating modes of the unit, including disconnection from the network.

In total, there will be more than 200 such tests. At present, the unit's reactor power is being raised to 75% of the nominal one.

Last modified on Wednesday, 31 May 2023
© 2010- State enterprise «Belarusian NPP». All rights reserved. At any use of materials of the web-site, the active reference is obligatory on www.belaes.by.
The web-site operates error-checking system. If you find a mistake, highlight it and press Ctrl + Enter.
Яндекс.Метрика
Development of CVR-Oktjabr'skij
Send a mistake message