Tuesday, 11 July 2023

The second power unit of BelNPP is connected to the network

Written by Department of information and public relations

On July 10 at 21.48, the second power unit of Belarusian nuclear power plant was connected to the network after the successful completion of scheduled tests of the reactor cooldown modes as part of the pilot operation program.

A phased increase in reactor power is running.

In accordance with the further program of work at the second power unit, dynamic tests will be carried out at various power levels with unloading of the power unit, including to zero level, followed by an assessment of the characteristics of the equipment before its comprehensive testing at design capacity.